CMMI-based Pre-Appraisal (Class C) - EXAMPLE
The on-site period will consist of:
·Walkthrough of Documented Processes at the organizational, project and instantiation level
·Conducting of interviews for Senior Managers, Middle Managers, Project Leaders, and Practitioners
·Consolidation of notes into observations and eventually findings and recommendations
·Development of the Senior Management Presentation
·Senior Management Presentation for the entire set of participants including the senior management team
The entire assessment team works together as a unit for all activities of the assessment.
CMMI-based Class C Appraisal Sample Schedule of Events
1 Day Pre-Appraisal Training ( Overview of AFA Method)
1 Day Documentation Review
4 Days Pre-Appraisal On-Site Period (As described below)
- ½ Day Project Manager Interview 1 (2 Project Managers)
- ½ Day Project Manager Interview 2 (2 Project Managers)
- ½ Day Practitioner Interview – Requirements & Architecture
- ½ Day Technical Solution
- ½ Day Integration and Systems Test
- ½ Day Quality Assurance, Configuration Management, Metrics, Processes
- ½ Day Draft Findings Generation
- ½ Day Senior Management Presentation (Practitioners, Project Managers,
Middle Managers, Senior Managers)
ASSUMPTION: Project Manager Interviews could be conducted in a “group” format – at least two of the project managers sould be comfortable being interviewed with another project manager in the room. The standard schedule has a separate interview with each Project Manager.
ASSUMPTION: The one day allocated for documentation is adequate for this surface level appraisal. If a more detailed look at documentation is needed add one more day.